Length of Bridge: |
80 mt |
Height of Bridge: |
6 mt |
RC Piles (Dia. 1000 mm): |
1.850 mt |
Prestressed Beams ( L: 20 mt): |
48 ea |
Excavation: |
107.000 m3 |
Filling & Compacting: |
53.000 m3 |
Subbase: |
12.000 m3 |
Base: |
19.000 tn |
Sidewalks: |
9.000 m2 |
Curbs |
13.000 mt |
Formwork: |
11.500 m2 |
Scaffolding: |
1.600 m3 |
Rebar: |
640 tn |
Concrete: |
5.500 m3 |
Sewerage and Storm water lines (Dia 300/600 mm): |
2.600 mt |
Electrical Cabling (LV / MV): |
3.100 mt |
Street Lighting Pole: |
42 ea |
Grassing: |
53.000 m2 |
Planting: |
21.000 ea |
Sprinkler system: |
14.500 mt |